
The Capital Engineering branch is responsible for various engineering projects throughout the Town of East Gwillimbury (EG), outside of new development/unassumed areas.
To view the Road Construction and Capital Engineering projects check out our Interactive Map.
Project descriptions and frequently asked questions (FAQ's) are provided for the following Capital Engineering projects:
Mount Albert Storm Outfalls and Trail Restoration |
|
Project Background: This storm outfall and trail restoration project is in the community of Mount Albert, adjacent to Vivian Creek Park. There are four storm outfalls and one span of trail in need of repair. Town staff have investigated and continue to monitor the condition of the outfalls, although they require repair, the current state is stable and interim holding repairs will be completed (if necessary) until construction takes place. Similarly, the slope behind 13 and 15 Valley Mills Road was also inspected, monitored, and deemed stable. Vivian Creek Trail Feedback Thank you to everyone who completed the Vivian Creek Trail Closure survey. Your thoughts and feedback have been incorporated into a staff memo for Council. The memo was presented to Committee of the Whole on July 25, 2023, to view the Agenda, please visit the Council meeting portal.
Trail Restoration Location:
The map below outlines the trail and storm outfall locations. This project has several complex
Next Steps:
Public Engagement:
Project Notices: Council Reports and Memos: |
Asphalt Resurfacing & Reconstruction |
|
Resurfacing is complete at the following location.
The following locations are scheduled for Fall 2025:
The following locations are scheduled for Spring 2026:
Construction work has begun with work anticipated to be completed by the end of 2025. |
Road Reconstruction Design |
|
The following locations have detailed designs that are scheduled to begin in 2026:
Queensville Sideroad and Centre Street Intersection (Detailed Design) This site previously had a preliminary design completed, and a public information centre (PIC) was held on Wednesday, December 6, 2023. Project maps and PIC presentation materials are below for your reference:
Grist Mill Subdivision (Detailed Design)
Before surveying and investigation work begins, area residents will receive a notice with further details. Questions? If you have feedback or questions for the project team, please contact them by email.
|
Bridge Rehabilitation - Design and Construction |
DesignThe following locations have detailed designs that are planned:
ConstructionYork Durham Line Bridge 113 (approx. 650m south of Holborn Rd.) and York Durham Line Bridge 114 (approx. 700m north of Holborn Rd.):
Queensville Sideroad Bridge 110 (approx. 100m east of Highway 48)
|
New Sidewalk Construction |
| The following location is scheduled for new sidewalk construction:
Highway 48 (Princess St. to Foodland)
|
New Sidewalk Design |
|
The following locations currently have designs underway: Mount Albert Road (Tyson Drive walkway to Grist Mill Rd)(P-18-02) Queensville Sideroad (Holland River bridge to Yonge St)(P-18-02)
Mount Albert Road (Conn Drive to EG Sports Complex, North Side Only)(Q-22-02)
|
Miscellaneous Concrete Repairs (Sidewalks & Curbs) |
|
Various locations throughout Town, identified through annual inspections.
|
Streetlight Pole Rehabilitation |
|
Steel streetlight poles identified for repair and replacement through inspections completed in 2023/ 2024.
|
Master Plans |
Downtown Mount Albert Revitalization |
Yonge Street Revitalization |
New Multi-Use Path and Lighting |
|
The following limits have a completed detailed design:
The following are approved construction limits:
Council Memos and Reports
Public Information Centre (PIC) Thank you to everyone who attended the joint PIC on June 28, 2023 at the Holland Landing Community Centre. Proposed project layouts are below for your reference: Questions? If you have feedback or questions for the project team, please contact them by email.
|
Water Rehabilitation Program |
|
A detailed design is underway for the following locations:
Sharon Watermain Replacement
A public information centre (PIC) was held on Wednesday, August 20, 2025. Project maps and PIC presentation materials are below for your reference:
Design contract preparation is underway for the following locations:
New Watermain Design, Secondary Watermain for West Holland Landing
Installation of New Fire Hydrants at Strategic Locations
|
Once the individual construction projects above are awarded, a copy of the Notice of Work will be uploaded into the table for reference.
For more information on current and upcoming regional construction projects in East Gwillimbury, please visit York Region's website.
The Government of Canada provides funding to Municipalities with Gas Tax Funding for a variety of different project categories including local roads and bridges. From the Town's Capital Budget, the following Road Construction and Capital Engineering projects have received this funding:
Road Rehabilitation Program
Miscellaneous Concrete Rehabilitation
York Durham Line Bridges - Rehabilitation
Click the puzzle pieces to learn more about this project.
for members of the public to review and provide feedbackOur Customer Service Team is here to help!