| Completed Activities |
- Request for Tender (RFT) Awarded
- Surveying and subsurface utility exploration works along the main corridor.
|
| July 7, 2025 |
- The contractor will mobilize some equipment (weather permitting) and complete assessments of the entire work area and layouts. This includes pre-construction photos of the work area and properties fronting the work area. Once completed, they will begin installing temporary construction fencing and safety signage for pedestrian access.
- Delivery of notices to residents.
|
|
July 14, 2025
|
- The contractor will continue with temporary construction fence installation and signage as needed.
|
|
July 21, 2025
|
- Ongoing surveying is taking place.
- The contractor will continue with temporary construction fence installation and signage as needed.
- The contractor will start removal work and provide advance notice for residents directly affected by this work where alternative access will be needed.
|
|
July 28, 2025
|
|
|
|
August 4, 2025
|
- Installation of erosion control fencing, catch basin sediment traps and tree protection.
- Installation of temporary overhead utilities by Guild Electric at the intersection of Yonge St and Mt Albert Rd/Queen St, involving lane restriction traffic control measures and a paid duty officer.
- Installation of temporary poles and guy wires by Guild Electric at the intersection of Yonge St and Thompson Dr/Bradford St.
|
|
August 11, 2025
|
- Completing the installation of tree protection fencing and catch basin sediment traps.
- Completion of the temporary utilities by Guild Electric, including energization at Yonge St. and Mount Albert Rd./Queen St.
- Completion of staging area at Doane Road West and Landing Court.
- Implementation of traffic controls measures.
|
|
August 18, 2025
|
- Completing the installation of tree protection fencing south of Doane Road.
- Guild Electric to complete energization of temporary streetlights at Yonge St and Mount Albert Rd/Queen St.
- Trisan Construction to mobilize equipment Wednesday and commence daylighting and water main servicing at Yonge and Mount Albert Rd/Queen St.
|
|
August 25, 2025
|
- Guild Electric is completing the energization of temporary streetlights at the intersection of Mount Albert Rd/Queen St and Yonge St.
- Trisan to commence water main mainline installation at the intersection of Mount Albert Rd/Queen St and Yonge St.
- Commence layout and installation of the balance of the erosion controls.
|
|
September 2, 2025
|
- Trisan crew #1 continuing with watermain installation at Yonge and Queen/Mount Albert intersection will proceed northbound towards School Street
- Commencement of tree removals by Nature's Shade Tree Care Inc.
- Layout and installation of the balance of erosion and sediment control fence
|
| September 8,2025 |
- Trisan continuing with watermain installation at Yonge and Queen/Mount Albert intersection and will proceed northbound towards School Street. Installation of catch basin structures on the east side of Yonge Street.
- Continuation of tree removals by Nature's Share Tree Care Inc.
- Layout and installation of the balance of erosion and sediment control fencing.
- Asphalt trench restoration on Yonge Street
|
| September 15, 2025 |
- Trisan continuing with watermain installation on Yonge street and will proceed northbound from School Street.
- Continuation of tree removals by Nature's Share Tree Care Inc.
- Layout and installation of the balance of erosion and sediment control fencing.
- Asphalt trench restoration on Yonge Street
|
|
September 22, 2025
|
- Trisan continuing with watermain installation on Yonge Street and will proceed northbound from North Street.
- Continuation of tree removals by Nature's Share Tree Care Inc.
- Layout and installation of the balance of erosion and sediment control fencing.
- Asphalt trench restoration on Yonge Street
|
|
September 29, 2025
|
- Trisan continuing with watermain installation on Yonge Street will proceed northbound from Walker Road.
- Layout and installation of the balance of erosion and sediment control measures
- Asphalt trench restoration on Yonge Street
|
|
October 6, 2025
|
- Trisan continuing with Watermain installation on Yonge Street will proceed northbound entering Thompson and Bradford Street intersection.
- Asphalt trench restoration on Yonge Street.
|
|
October 14, 2025
|
- Trisan continues with watermain installation on Yonge Street proceeding northbound, north of Thompson Drive intersection.
- Trisan completing storm sewer installation and grading works South of Doane Road.
- Asphalt trench restoration on Yonge Street.
|
|
October 20,2025
|
- Trisan continues with watermain installation on Yonge Street in the area of 19466 Yonge Street.
- Completing hydrant installation and road crossings
|
|
October 27, 2025
|
- Installation of water services on Thompson Drive
- Culvert Creek works to begin
- Watermain Commissioning by IQ Environmental
- Guild electrical onsite completing midblock lighting installation
- Asphalt restoration on roads and sidewalks
|
|
November 3, 2025
|
- Installation of Storm Sewers
- Culvert Creek works continue
- Watermain realignment south of Doane Road
- Watermain Commissioning by IQ Environmental
|
|
November 10, 2025
|
- Watermain connection Bradford & Yonge Street
- Water service switch over starting south of Bradford Street continuing southbound to North Street
- Installation of storm sewers
- Asphalt restoration
|
|
November 17, 2025
|
- Watermain Connection at Bradford and Yonge Street
- Water Service switch over starting south of Bradford Street continuing southbound to North Street
- Asphalt Restoration
|
|
November 24, 2025
|
- Water service switch over continuing south from Bradford Street to North Street- Residents can expect to see open excavation across the street to each water service. Works could involve removal of asphalt or curb to facilitate connection to new service.
|
| December 1, 2025 |
- Water service switch over continuing south from Walker Road - Residents can expect to see open excavation across the street to each water service. Works could involve removal of asphalt, sidewalk, curb to facilitate connection to new service.
- Watermain tie in at Walker Road, North Street and School Street (Connecting new watermain to existing) - Residents can expect to see open excavation at the intersections.
- Fire Hall service connection - New water service connection for Fire Hall residents can expect to see open excavation along frontage of Fire Hall.
- Asphalt Restoration continues
- Guild Electric onsite- Mid block lighting conduit installation and signalization installations
|
|
December 8, 2025
|
- Watermain tie in at Queen Street and Mt. Albert Road (Connecting new watermain to existing) -Residents can expect to see open excavation at intersections East and West side of Yonge Street.
- Water service switch overs north of Bradford Street - Residents can expect to see open excavation works extending across the street to each water service. Works could involve removal of asphalt, sidewalk, curb to facilitate connection to new service.
- After hours watermain tie in at 19466 Yonge Street Thursday night. (Connecting new watermain to existing)
- Guild Electric onsite- Temporary signalization at Bradford and Thompson & Doane Road intersection signalization installations
|
|
December 15, 2025
|
- Valve box repair Peter Street and North Street
- Removal and decommissioning of existing valves boxes and chambers- residents can expect to see open excavation on the east side of Yonge removing old infrastructure
- Asphalt restoration continues
- IQ Environmental Inc. onsite completing hydrant flow testing
- Guild Electric Ltd. onsite completing Braford temporary signal installation
- Opening of Yonge Street and side streets for holiday
|
|
January 5, 2026
|
- Guild Electric Ltd. onsite
- Curb removal for storm sewer installation
|
|
January 13, 2026
|
- Removals (curb, sidewalk) along Yonge Street between Queen Street and Bradford Street
- Road saw cutting in preparation for storm installation between Queen Street and Bradford Street
- Guild Electric Ltd. onsite directional drilling north of Bradford Street
|
|
January 19,2026
|
- Removals (curb,sidewalk) along Yonge Street continues
- Installation of storm sewer has started at Bradford Street continuing south, residents can expect lane reductions with open excavation.
- Guild Electric Ltd. onsite directional drilling continues north of Bradford Street
|
|
January 26,2026
|
- Installation of storm sewer continues between Bradford Street and Mt. Albert. Residents can expect lane reductions with open excavation.
- Asphalt restoration
|