| Completed Activities |
- Request for Tender (RFT) Awarded
- Surveying and subsurface utility exploration works along the main corridor.
|
| July 7, 2025 |
- The contractor will mobilize some equipment (weather permitting) and complete assessments of the entire work area and layouts. This includes pre-construction photos of the work area and properties fronting the work area. Once completed, they will begin installing temporary construction fencing and safety signage for pedestrian access.
- Delivery of notices to residents.
|
|
July 14, 2025
|
- The contractor will continue with temporary construction fence installation and signage as needed.
|
|
July 21, 2025
|
- Ongoing surveying is taking place.
- The contractor will continue with temporary construction fence installation and signage as needed.
- The contractor will start removal work and provide advance notice for residents directly affected by this work where alternative access will be needed.
|
|
July 28, 2025
|
- Ongoing surveying is taking place. Temporary traffic signalization at intersections is being laid out by the surveyor and the electrical contractor.
- The contractor will continue with temporary construction fence installation and signage as needed
|
|
August 4, 2025
|
- Installation of erosion control fencing, catch basin sediment traps and tree protection.
- Installation of temporary overhead utilities by Guild Electric at the intersection of Yonge St and Mt Albert Rd/Queen St, involving lane restriction traffic control measures and a paid duty officer.
- Installation of temporary poles and guy wires by Guild Electric at the intersection of Yonge St and Thompson Dr/Bradford St.
|
|
August 11, 2025
|
- Completing the installation of tree protection fencing and catch basin sediment traps.
- Completion of the temporary utilities by Guild Electric, including energization at Yonge St. and Mount Albert Rd./Queen St.
- Completion of staging area at Doane Road West and Landing Court.
- Implementation of traffic controls measures.
|
|
August 18, 2025
|
- Completing the installation of tree protection fencing south of Doane Road.
- Guild Electric to complete energization of temporary streetlights at Yonge St and Mount Albert Rd/Queen St.
- Trisan Construction to mobilize equipment Wednesday and commence daylighting and water main servicing at Yonge and Mount Albert Rd/Queen St.
|
|
August 25, 2025
|
- Guild Electric is completing the energization of temporary streetlights at the intersection of Mount Albert Rd/Queen St and Yonge St.
- Trisan to commence water main mainline installation at the intersection of Mount Albert Rd/Queen St and Yonge St.
- Commence layout and installation of the balance of the erosion controls.
|
|
September 2, 2025
|
- Trisan crew #1 continuing with watermain installation at Yonge and Queen/Mount Albert intersection will proceed northbound towards School Street
- Commencement of tree removals by Nature's Shade Tree Care Inc.
- Layout and installation of the balance of erosion and sediment control fence
|
| September 8,2025 |
- Trisan continuing with watermain installation at Yonge and Queen/Mount Albert intersection and will proceed northbound towards School Street. Installation of catch basin structures on the east side of Yonge Street.
- Continuation of tree removals by Nature's Share Tree Care Inc.
- Layout and installation of the balance of erosion and sediment control fencing.
- Asphalt trench restoration on Yonge Street
|
| September 15, 2025 |
- Trisan continuing with watermain installation on Yonge street and will proceed northbound from School Street.
- Continuation of tree removals by Nature's Share Tree Care Inc.
- Layout and installation of the balance of erosion and sediment control fencing.
- Asphalt trench restoration on Yonge Street
|
|
September 22, 2025
|
- Trisan continuing with watermain installation on Yonge Street and will proceed northbound from North Street.
- Continuation of tree removals by Nature's Share Tree Care Inc.
- Layout and installation of the balance of erosion and sediment control fencing.
- Asphalt trench restoration on Yonge Street
|
|
September 29, 2025
|
- Trisan continuing with watermain installation on Yonge Street will proceed northbound from Walker Road.
- Layout and installation of the balance of erosion and sediment control measures
- Asphalt trench restoration on Yonge Street
|
|
October 6, 2025
|
- Trisan continuing with Watermain installation on Yonge Street will proceed northbound entering Thompson and Bradford Street intersection.
- Asphalt trench restoration on Yonge Street.
|
|
October 14, 2025
|
- Trisan continues with watermain installation on Yonge Street proceeding northbound, north of Thompson Drive intersection.
- Trisan completing storm sewer installation and grading works South of Doane Road.
- Asphalt trench restoration on Yonge Street.
|
|
October 20,2025
|
- Trisan continues with watermain installation on Yonge Street in the area of 19466 Yonge Street.
- Completing hydrant installation and road crossings
|
|
October 27, 2025
|
- Installation of water services on Thompson Drive
- Culvert Creek works to begin
- Watermain Commissioning by IQ Environmental
- Guild electrical onsite completing midblock lighting installation
- Asphalt restoration on roads and sidewalks
|
|
November 3, 2025
|
- Installation of Storm Sewers
- Culvert Creek works continue
- Watermain realignment south of Doane Road
- Watermain Commissioning by IQ Environmental
|
|
November 10, 2025
|
- Watermain connection Bradford & Yonge Street
- Water service switch over starting south of Bradford Street continuing southbound to North Street
- Installation of storm sewers
- Asphalt restoration
|
|
November 17, 2025
|
- Watermain Connection at Bradford and Yonge Street
- Water Service switch over starting south of Bradford Street continuing southbound to North Street
- Asphalt Restoration
|
|
November 24, 2025
|
- Water service switch over continuing south from Bradford Street to North Street- Residents can expect to see open excavation across the street to each water service. Works could involve removal of asphalt or curb to facilitate connection to new service.
|
| December 1, 2025 |
- Water service switch over continuing south from Walker Road - Residents can expect to see open excavation across the street to each water service. Works could involve removal of asphalt, sidewalk, curb to facilitate connection to new service.
- Watermain tie in at Walker Road, North Street and School Street (Connecting new watermain to existing) - Residents can expect to see open excavation at the intersections.
- Fire Hall service connection - New water service connection for Fire Hall residents can expect to see open excavation along frontage of Fire Hall.
- Asphalt Restoration continues
- Guild Electric onsite- Mid block lighting conduit installation and signalization installations
|
|
December 8, 2025
|
- Watermain tie in at Queen Street and Mt. Albert Road (Connecting new watermain to existing) -Residents can expect to see open excavation at intersections East and West side of Yonge Street.
- Water service switch overs north of Bradford Street - Residents can expect to see open excavation works extending across the street to each water service. Works could involve removal of asphalt, sidewalk, curb to facilitate connection to new service.
- After hours watermain tie in at 19466 Yonge Street Thursday night. (Connecting new watermain to existing)
- Guild Electric onsite- Temporary signalization at Bradford and Thompson & Doane Road intersection signalization installations
|
|
December 15, 2025
|
- Valve box repair Peter Street and North Street
- Removal and decommissioning of existing valves boxes and chambers- residents can expect to see open excavation on the east side of Yonge removing old infrastructure
- Asphalt restoration continues
- IQ Environmental Inc. onsite completing hydrant flow testing
- Guild Electric Ltd. onsite completing Braford temporary signal installation
- Opening of Yonge Street and side streets for holiday
|
|
January 5, 2026
|
- Guild Electric Ltd. onsite
- Curb removal for storm sewer installation
|
|
January 13, 2026
|
- Removals (curb, sidewalk) along Yonge Street between Queen Street and Bradford Street
- Road saw cutting in preparation for storm installation between Queen Street and Bradford Street
- Guild Electric Ltd. onsite directional drilling north of Bradford Street
|
|
January 19,2026
|
- Removals (curb,sidewalk) along Yonge Street continues
- Installation of storm sewer has started at Bradford Street continuing south, residents can expect lane reductions with open excavation.
- Guild Electric Ltd. onsite directional drilling continues north of Bradford Street
|
|
January 26,2026
|
- Installation of storm sewer continues between Bradford Street and Mt. Albert. Residents can expect lane reductions with open excavation.
- Asphalt restoration
|
|
February 2, 2026
|
- Installation of storm sewer continues between Bradford Street and Mt. Albert. Residents can expect lane reductions with open excavation.
- Asphalt Restoration
|
|
February 9, 2026
|
- Installation of storm sewer continues between Bradford Street and Mt. Albert. Residents can expect lane reductions with open excavation.
- Installation of Storm sewer at the intersection of Mt. Albert and Queen Street is expected to start this week. Residents can expect traffic disruptions with open excavation.
- Asphalt Restoration
|
|
February 16, 2026
|
- Installation of storm sewer continues between Bradford Street and Mt. Albert . Residents can expect lane reductions and temporary disruptions with open excavation.
- Installation of storm sewer continues at the intersection of Mt. Albert and Queen Street residents can expect lane reductions and closures as pipe is installed across intersection.
- Asphalt restoration
|
|
February 23, 2024
|
- Installation of storm sewer continues at the intersection of Mt. Albert and Yonge Street. Residents can expect open trench excavation with lane reductions as pipe is installed across the road and along the shoulder.
- Installation of storm sewer, north of Thompson has commenced. Residents can expect open trench excavations with lane reductions as pipe and structures are installed.
- Asphalt restoration
-
|